Maintenances and incidents regarding our services, networks and datacenters can be followed here.
Following a bug identified on a specific switch, we are scheduling a maintenance on it on October 4th.
This switch is in charge of the RPN network on 2 different racks : D1 and D2.
Impacted racks : RPN network on D1 / D2 in DC5-A
Start time : Between 04/10/18 0700Z (0900LT) and 0730Z (0930LT)
Expected downtime : 20 minutes
We will update this status when the maintenance starts.
We will carry out the semi-annual preventive maintenance of CRAC units from September 3rd to October 4th, 2018. CRAC units will be shut down one at a time, so as not to impact the cooling of halls. Each IT zone has CRAC unit called «backup»: each CRAC unit is doubled. Each MVLB hall has a main air hanling unit (AHU).
The maintenance will be done according to the following schedule:
Impacts on services : Loss of cooling redundancy during the preventive maintenance operation of aCRAC unit (max 1h). No impact on the cooling of facilities. The maximum cut-off time per CRAC unit is otherwise defined at 1 hour
Thanks for your understanding
We are scheduling an electrical maintenance on TGBT1. It should not have any impact on availability, but some power redundancy will be down.
Maintenance will start on October 11th 2018, at 11:00PM UTC, and last around 7 hours (until October 12th, at 6:00AM UTC).